U.S. Department of the Interior
•Read full article
Greenlink transmission lines, multiple solar facilities move toward completion.
Greenlink West Transmission Project and Libra Solar Project will unlock up to 4.7 gigawatts of clean energy, enough to power nearly 5 million homes.
Administration has released new data to demonstrate how the historic steps it has taken to accelerate and improve federal permitting processes are helping deliver more projects, more efficiently.
Libra Solar Project will be the largest solar-plus battery energy storage project in Nevada and one of the largest in the United States .
Bonanza Solar Project would include battery storage and a 5.4-mile gen-tie line on approximately 5,133-acres of public lands in Clark and Nye counties, near Las Vegas .
Greenlink North Transmission Project could unlock up to 4,000 megawatts of clean energy.